Selang Khola Hydropower Project

LOCATION

Jugal Rural Municipality, Sindhupalchowk

INSTALLED CAPACITY

990 kW

TOTAL PROJECT COST

NPR 25cr

Established Date

March 5, 2006

Key technical Features

Energize Society With Sustainable And Reliable
Energy Systems!

Installed Capacity

990 kW

Annual Energy Output

6.77 GWh

Power Purchase Agreement (PPA)

Signed with Nepal Electricity Authority (NEA)

Operational Since

[Bhadra, 2081]

Type

Run-of-River Hydropower Project

Project Cost

NPR 25cr

Status of Work Performed

Generation License

Completed

Environmental Impact Assessment (EIA)

Completed

Power Purchase Agreement (PPA)

Concluded

Power Purchase Agreement (PPA)

Concluded

PPA Terms

 6/6 months agreement

Access Road

Completed

Construction Power

Completed

Camp

Acquired

Civil Contractor

Mobilized

EM Contractor

Selected

TL Contractor

Selected

HM supplies

Completed